Skip to content

Allocating Workers to Jobs

Allocating workers to scheduled jobs ensures the right people are assigned to the right work at the right time.

The primary way to allocate workers is by dragging scheduled items on the calendar:

  1. Click and hold a scheduled item
  2. Drag it to the desired date, time, and resource lane
  3. Release to drop it

When you drop an item, Vera automatically:

  • Validates the proposed time slot
  • Checks for resource conflicts (employee availability)
  • Verifies required certifications
  • Calculates travel time between locations

If there are conflicts, a modal dialog appears showing the issues and letting you confirm or cancel the move.

Screenshot: The conflict resolution modal showing employee availability indicators (green/red/amber), certification checks, and Accept/Cancel buttons.

The allocation panel shows two views:

By Staff Lists each employee with their assigned tasks, showing:

  • Employee name and reference
  • Tasks assigned to them
  • Minutes allocated for “This” visit vs “All” visits (cumulative)
  • Progress gauges for task completion

By Task Lists each task with its employee assignments, showing:

  • Task reference with progress gauge (Allocated vs Required)
  • Employee names assigned
  • Individual time allocations

Choose how time is allocated using the mode buttons:

  • Sequence - Allocate jobs for consecutive days
  • Date Only - Allocate for a single date only
  • Single Span - Allocate total duration across a selected period

When a conflict is detected, the conflict modal shows:

  • Which employees are affected
  • The nature of the conflict (availability, certifications, travel time)
  • Visual indicators (green/red/amber) for each employee’s status
  • Options to accept or cancel the allocation